MINISTRY OF ELECTRIC POWER

Breaking News :

Yangon Division


Under Construction Projects of Lines and Substations in Yangon Division

No

Name of Project 

Substation MVA Location
1

230kV Wartayar –( Ywarma – Hlaingtharyar) -

Line (8) Miles & Wartayar Substation 

Wartayar Substation Switchbay

Yangon Division, Shwe Pyi Thar

Township, Htantabin Township

2

230kV Wartayar – Hlawga Line (10 Miles) &

Switchbay Extension

Wartayar

Hlawga 

Switchbay

Switchbay

Yangon Division,Shwe Pyi Thar

Township & Mingalardon Township 

3

230kV Khanaungto Substation

Khanaungto Switchbay

 Yangon Division,

Sategyikhanaungto Township 

 

(1) 230kV Wartayar – Hlawga Line (10 Miles) & Switchbay Extension

1. Location                                                 -   Yangon Division, Shwe Pyi Thar Township & Mingalardon Township

2. Scope of Work                                        

(A) Substation

  230kV Switch Bay (Wartayar Substation)   -   (2) Bays

  230kV Switch Bay (Hlawga Substation)     -   (2) Bays    

(B) Line

    230kV Line                                                -   (10) Miles

3. Situation of Signing Contract                       

 Contract No. & Date (Material)                    -   38/DPTSC(PTP)/2019-2020 (3.6.2020)

 Contractor                                                    -   Khin Maung Nyunt Trading Co., Ltd.

 Contract No. & Date (Foundation,Erection) -   78/DPTSC(PTP)/2020-2021 (7.10.2021)

    Contractor                                                 -   Zeya & Associates Co., Ltd.

    Project Manager (1) + (Civil) Southen

4.Starting Date of Project (Effective Date)-   (7.10.2021)

5.Ending Date of Project (Approximation)-   (6.10.2023)

6.Complete Situation                                  -   Excavation  -   45% 

                                                                          Foundation -   32%

                                                                          Erection      -   13%

 

(2) 230kV Khayan – (Thilawar - Kamarnad) Line In/ Out (0.6) Miles & Substation

1. Location                                                    -   Yangon Division, Khayan Township & Thonegwa

2. Scope of Work                                             

(A) Substation

    230kV Line Bay                                          -   (4) Bays

    230kV Bus Coupler                                    -   (1) Bay

    230kV Transformer Bay                             -   (2) Bays

    230kV Measuring Bay                                -   (2) Bays

    230kV Single Phase Transformer              -   (6) Nos

    33kV Line Bay                                            -   (10) Bays

    33kV Transformer Bay                               -   (2) Bays

    33kV Measuring Bay                                  -   (2) Bays

    33kV Bus Section Bay                               -   (1) Bay     

    E-Type                                                       -   (1) No

(B) Line

    230kV Line In /Out                                     -   (0.6) Miles

3. Situation of Signing Contract                  

    Contract No. & Date (Material)                   -   87/DPTSC(PTP)/2019-2020 (15.6.2020)

    Contractor                                                  -   Zeya & Associates Co., Ltd.

    Contract No. & Date                                   -   77/DPTSC(PTP)/2020-2021 (24.9.2021)

                                                                           (Switchyard Foundation & E-Type Building)

    Contractor                                                  -   AhtinkayaCo., Ltd.

                                                                           Project Manager (1) + (Civil) Southen

4. Starting Date of Project (Effective Date)-   (24.9.2021)

                                                                            (SwitchyardFoundation & E-Type Building)

5. Ending Date of Project (Approximation)-   (23.9.2023)

                                                                            (SwitchyardFoundation & E-Type Building)

6. Complete Situation – Substation             -

(a) Civil Work                                                 -     All Total (96.977%)

(b) Electrical Installation                                 -   87.81%

(c) Line In/Out (0.6)Miles

    (i) Foundation                                             -   (4) Nos Finished  

    (ii) Erection                                                 -   (3) Nos Finished                                                                                      

(iii) Stringing                                                   -   (0.24) Mile  Finished       

 

(3) 230kV Khanaungto Substation

1. Location                                                 -   Yangon Division, Sategyikhanaungto Township

2. Scope of Work

Fence of Substation                                    -   (2510)ft Brickfence and Main Gate Door

(6620)ft Barbed Fence

3. Situation of Signing Contract

    Contract No. & Date                                -   81/DPTSC(PTP)/2020-2021

    Contractor                                              -   Power Heaven (28.9.2023)

4. Starting Date of Project (Effective Date)    -   (29.9.2021)

5. Ending Date of Project (Approximation)    -   (28.9.2023)

6. Complete Situation                                  -   Fence of Substation – (87.25%)

 

230kV Khanaung To Substation {Fence} Brick Fencing Work

 

(4) 230kV East Dagon – Hlawga Line (12.7) Miles & 230kV Switch Bay Extension at Hlawga Substation

1. Location                                                       -   Yangon Division, East Dagon Township,

                                                                              Mingalardon Township

2. Scope of Work

(A) Line                                                             -   (12.7) Miles                 

(B) Substation                                                   -   230kV Switch Bay (Hlawga) (2) Bay

2. Situation of Signing Contract

    Contact No. & Date (Material)                       -   86/DPTSC (PTP)/2019-2020(15.6.2020)

    Contractor                                                     -   Zeya & Associates Co., Ltd.

    Contact No. & Date (Foundation,Erection)   -   80/DPTSC(PTP)/2020-2021 (24.9.2021)

    Contractor                                                     -   IGE Power Co., Ltd.

                                                                              Project Manager (1)+(Civil) Southen

4. Starting Date of Project (Effective Date)   -   (24.9.2021)

5. Ending Date of Project (Approximation)   -  (23.9.2023)

6. Complete Situation                                     -   Foundation (5%)

 

Site Photo Records

 

 

 

 

 

(5) 500kV Pharyargyi - Hlaingtharyar Line (56.8) Mile

1. Location                                                     -   Bago Division, Yangon Division

2. Scope of Work                                           -   Line   -   (T - 55) to ( T - 226)

                                                                           (Survey approved) (In Yangon Division)

3. Situation of Signing Contract

    Contract No. & Date                                    -   3/ DPTSC (PTP) /2019-2020 (18.12.2019)

    Contractor                                                   -   Mitsubishi  Coporation Co., Ltd

4. Starting Date of Project (Effective Date) -   (16.1.2020)

5. Ending Date of Project (Approximation) -   (15.7.2023)

6. Complete Situation                                   -   (i) Excavation     -   (95) Nos  Finished

                                                                            (ii) Foundation   -   (90) Nos Finished

                                                                             (iii) Erection      -   (52) Nos Finished 

 

(6) 500kV Hlaingtharyar Substation

1. Location                                                        -   Yangon Division , Hlaingtharyar  Township

2. Scope of Work                                              -   500/230/33 KV , 2 x 500MVA  Substation    

3. Situation of Signing Contract                       

    Contract No. & Date                                       -   91/ DPTSC (PTP)/2019-2020 (16.6.2020)

    Contractor                                                      -   Sojitz Corporation

4. Starting Date of Project (Effective Date)    -   (16. 6. 2020)        

5. Ending Date of Project (Approximation)   -   (15. 6. 2023)

6. Complete Situation                                      -   Finished Sand Filling and Road

                                                                               Embankment for Switchyard – 100%

                                                                               Retaining Wall – 3.49 % 

 

(7) 230kV Pharyargyi – ( Kamanat - Myaungtagar )Line ( 8.7 )Mile

1. Location                                                             -   Bago Division , Yangon Division

2. Scope of Work                                                   -   Line  -   (T - 69) to (T- 109)

                                                                                     (In Yangon Division)

3. Situation of Signing Contract                       

    Contract No. & Date                                            -   10/DPTSC(PTP)/2021-2022 (9.3.2022)

    Contractor                                                           -   (Consortium of Kanaung Co., Ltd and

                                                                                    Integral Power Transmission Group Co., Ltd)

4. Starting Date of Project (Effective Date)        -   (9.3.2022)

5. Ending Date of Project (Approximation)        -   (8.3.2024)

6. Complete Situation                                           -   Excavation        -   (13)  Nos Finished                                                

                                                                                -   Foundation        -   (13) Nos Finished            

                                                                                -   Erection             -   (7) Nos Finished  

 

(8) 230kV Hlaingtharyar(West University) Substation

1. Location                                                        -    Yangon Division, Hlaingtharyar  Township

2. Scope of Work                                                   Switchyard Foundation & Additional Work

3. Situation of Signing Contract                       

   Contract No. & Date                                        -   17/ DPTSC (PTP)/2022-2023 (20 . 10 . 2022)

    Contractor                                                      -    Aye Chan Mon Co.,Ltd

4. Starting Date of Project (Effective Date)    -   20. 10. 2022

5. Ending Date of Project (Approximation)   -    19. 10. 2023 

6. Complete Situation                                      -    Foundation Work (79%)

                                                                           -    Electrical Installation (21.05%)

 

230kV Hlaingtharyar(West University) Substation