Under Construction Projects of Line and Substations in Bago Division
No |
Name of Projects |
Substation |
MVA |
Location |
1 |
230kV Saparkywei – Taungoo Line (9.5) miles and 230kV Toungoo Substation (2) Bays extension |
230kV Taungoo (2)Bays extension |
230/33/11kV, (3x20) MVA |
Bago Division (Taungoo Township , Oktwin Township) |
2 |
500kV Kankaung (Meiktila)- Saparkywei (Taungoo) Transmission Line Part II (72.51)Miles and 500kV Saparkywei Substation |
500kV Saparkywei Substation (1x500 MVA) |
500/230/33kV, (1x500)MVA |
Nay Pyi Taw (Ottarathiri Township , Dekkhina Thiri Township , Lewe Township) Bago Division (Taungoo Township, Yedashe Township) |
3 |
500kV Taungoo-Phayargyi (Kamarnat) Transmission Line (108.34) Miles and 500kV Phayargyi Substation |
500kV Phayargyi Substation (2x500 MVA) |
500/230/33kV, (2x500)MVA |
Bago Division (Taungoo Township , Oktwin Township ,Phyu Township , Kyauktagar Township , Daik-U Township ,Bago Township ) |
4 |
500kV Phayargyi –Hlaing Tharyar Transmission Line (14) miles |
- |
- |
(Bago Division ,Bago Township) |
5 |
230kV Phayargyi(Kamarnat)-Myaungtagar Transmission Line (23)miles |
- |
- |
(Bago Division ,Bago Township) |
6 |
230kV, (150) MVA Kamarnut Substation (New) In/ Out (Diversion) Transmission (1.283) miles |
230/66/11kV, (150) MVA Kamarnut Substation (Extension) |
(150) MVA |
Bago Region, Kamarnut Township |
7.A |
230kV Minhla – Athoke Transmission Line (101) miles |
230kV Switch Bay (3) Nos.Extension at Minhla Substation 230kV Switch Bay (2) Nos. Extension at Athoke Substation |
(150) MVA |
Bago Region, Minhla Township Ayeyarwaddy Region, Athoke Township |
7.B |
230kV Minhla Switchyard foundation & Fence |
230/66 kV Transformer Plinth Foundation 66kV Switchyard Bay Extension outgoing bay, bus bay, measuring bay, outgoing feeder (3) bays |
(150) MVA |
Bago Region, Minhla Township |
230kV Saparkywei - Taungoo Transmission Line (9.5) miles and
230kV Taungoo Substation (2) Bays Extension
1. Location - Bago Division , (Taungoo Township , Oktwin Township)
2. Scope of Work
(A) Line - (9.5) miles
(B) Substation - 230kV Switch Bay (2)Bays
3. Situation of Signing Contract
(A) Line
Construction - Project Manager (2) Office, Tharyargone (PTP)
Contract No. & Date(Materials) - 59/ DPTSC(PTP)/2019-2020 (3.6.2020)
Contractor - Khin Maung Nyunt Co.,Ltd
(B) Substation
Construction - Project Manager (2) Office, Tharyargone (PTP) & Project Manager (Civil) Southen
Contract No. & Date(Materials) - 83/ DPTSC(PTP)/2019-2020 (28.4.2020)
Contractor - Aye Chan Mon Co.,Ltd
4. Starting Date of Project (Effective date) - Line - (1.2.2020)
Substation - (20.12.2020)
5. Ending Date of Project (Approximation) - Line - June, 2022
Substation - November,2021
6. Complete Situation - Line - (100%)
Substation - (100%)
230kV Saparkywei - Taungoo Transmission Line (9.5) miles
230kV Taungoo Substation (2) Bays Extension
500kV Kankaung (Meiktila) – Saparkywei(Taungoo) Transmission Line Part II (72.51) miles and 500kV Saparkywei Substation
1. Location - Nay Pyi Taw (Ottarathiri Township,Dekkhina Thiri Township ,
Lewe Township) Bago Division (Taungoo Township , Yedashe Township)
2. Scope of Work
(A) Line - (72.51) miles
(B) Substation - 500/230/33kV (500MVA) x 1banks Tr
500/230/33kV 100MVAR Shunt Reactor ( 4 Unit)
3. Situation of Signing Contract
(A) Line
Contract No. & Date(Stringing) - 3/DPTSC(PTP)/2018-2019 (26.12.2018)
Contractor - SEPCO Co.,Ltd
Contract No. & Date(Foundation & Erection) - 295/DPTSC(PTP)/2013-2014 (25.1.2018)
Contractor - Dragon Emperor Co.,Ltd
Contract No. & Date(Foundation & Erection) - 296/DPTSC(PTP)/2013-2014 (16.7.2015)
Contractor - Minanawrathar Co.,Ltd
Contract No. & Date(Foundation & Erection) - 297/DPTSC(PTP)/2013-2014 (14.7.2015)
Contractor - Chan Hein Co.,Ltd
Contract No. & Date(Foundation & Erection) - 298/DPTSC(PTP)/2013-2014 (25.1.2018)
Contractor - Khin Maung Nyut Co.,Ltd
Contract No. & Date(Instruction Service) - 28/DPTSC(PTP)/2018-2019 (14.2.2019)
Contractor - KEPCO Co.,Ltd
Contract No. & Date(Supply of ACSR) - 37/DPTSC(PTP)/2018-2019 (11.3.2019)
Contractor - Zeya & Associates Co.,Ltd
(B) Substation
Contract No. & Date - 57/DPTSC(PTP)/2019-2020 (6.3.2020)
Contractor - Marubeni Corporation
4. Starting Date of Project (Effective date) - Line - (26.12.18)
Substation - 6.3.2020
5. Ending Date of Project (Approximation) - Line - October, 2023
Substation - September,2022
6. Complete Situation - Line - 100 %
Substation - 24.19 % (Civil Work)
500kV Kankaung (Meiktila) – Saparkywei(Taungoo) Transmission Line (72.51) miles
500kV Saparkywei Substation
500kV Taungoo-Pharyargyi (Kamanat) Transmission Line (108.34) Miles and Substation
1. Location - Bago Division , (Taungoo Township , Oktwin Township , Phyu Township ,
Kyauktagar Township , Daik-U Township , Bago Township )
2. Scope of Work
(A) Line - (108.34) miles
(B) Substation - 500/ 230 kV (500 MVA) x 2 banks Tr
500kV 100MVAR Shunt Reactor (2 Unit)
3. Situation of Signing Contract
(A) Contract No. & Date - 56/ DPTSC(PTP)/ 2018-2019 (25.6.2019)
Contractor - Doosan Engineering & Construction Co.,Ltd
(B) Substation
Contract No. & Date - 3/DPTSC(PTP)/2019-2020 (18.12.2019)
Contractor - (Sojitz Co.,Ltd)
4. Starting Date of Project(Effective date) - Line - (25.6.2019)
- Substation - (16.1.2020)
5. Ending Date of Project (Approximation) - Line - June, 2023
- Substation - (15.1.2023)
6. Complete Situation - Line - (92.225%)
- Substation - (10.6%) (Civil Work)
500kV Toungoo-Pharyargyi (Kamanat) Transmission Line (108.34)Miles
Pharyargyi Substation
500kV Phayargyi – Hlaing Tharyar Transmission Line (14) miles
1. Location - Bago Division , (Bago Township)
2. Scope of Work
(A) Line - (14) miles
3. Situation of Signing Contract
(A) Line
Contract No. & Date - 3/DPTSC(PTP)/2019-2020 (18.12.2019)
Contractor - Mitsubishi Coporation
4. Starting Date of Project (Effective date) - Line - (16.1.2020)
5. Ending Date of Project (Approximation) - Line - (15.7.2022)
6. Complete Situation - Line - (79.94 %)
500kV Phayargyi – Hlaing Tharyar Transmission Line
230kV Phayargyi (Kamarnat) - Myaungtagar Transmission Line (23)miles
1. Location - Bago Division , (Bago Township )၊ Yangon Division , Hlaing Tharyar Township
2. Scope of Work
(A) Line - (23) miles
3. Situation of Signing Contract
(A) Line
Contract No. & Date(Materials) - 10/DPTSC(PTP)/2021-2022 (9.3.2022)
Contractor - The Consortium of Kanaung & Integral Power Transmission Group Co,Ltd
4. Starting Date of Project (Effective date) - Line - (9.3.2022)
5. Ending Date of Project (Approximation) - Line - (9.3.2024)
6. Complete Situation - Line - (48.13%)
230kV Phayargyi(Kamarnat)-Myaungtagar Transmission Line (23)miles
230/66/11kV, (150) MVA Kamarnut Substation (Extension)
1. Location - Bago Division (Front), Kamarnut Village
2. Scope of Work
Substation
230kV Incoming Bay - 4 Bays
230kV Transformer Bay - 1 Bay
230kV Bus Coupler Bay - 1 Bay
230kV Measuring Bay - 2 Bays
66kV Incoming/Main - 1 Bay
66kV Outgoing Bay - 5 Bays
66kV Measuring Bay - 1 Bay
3. Situation of Signing Contract
Contract No.&Date(Construction) - Project Manager(3)+(Civil) Southen
Contract No.& Date(Materials) - 73(T)/ESE/2019-2020 (4.2.2020)
Contractor(Materials) - Zillion Luck Engineering Co.,Ltd
Contractor(Transformer) - KhinMaungNyuntCo.,Ltd
4. Starting Date of Project (Effective date) - (15.1.2021)
5. Ending Date of Project (Approximation) - (31.10.2022)
6. Complete Situation
Switchyard foundation (Civil Work) - (100%)
Substation (Installation) - (78.8 %)
230/66/11kV, (150) MVA Kamarnut Substation (Extension)
(A) 230kV Minhla – Athoke Transmission Line (101) miles and Minha &
Athoke Substations Extension
1. Location :- Bago and Ayeyarwaddy Region
2. Scope of Work -
(A) Line - 101 miles
(B) Substation -
- 230kV Switch Bay (3) Nos.Extension at Minhla Substation
- 230kV Switch Bay (2) Nos. Extension at Athoke Substation
3. Situation of Signing Contract
Line/ Substation
Construction - Khin Maung Nyunt TradingCo.,Ltd. and TBEA Co.,Ltd.
Contract No.& Date(Materials) - 95/DPTSC (PTP)/2019-2020 dated 09.07.2020
Contractor - Consortium of Khin Maung Nyunt Trading Co.,Ltd. and TBEA Co.,Ltd.
4. Contract Effective Date of Project - 10.08.2020
5. Completion Date of Project - 09.08.2023
(Approximation)
6. Complete Situation
Transmission Line - 0 % (Finalized Line Route, Tower Type F approved)
Substation - 0 %
(B) 230kV Minhla Switchyard foundation & Fence
1. Location - : Bago Region.
2. Scope of Work -
- 230/66 kV Transformer Plinth Foundation
- 66 kV Switchyard Bay Extension outgoing bay, bus bay, measuring bay, outgoing feeder (3) bays
3. Situation of Signing Contract
Substation
Construction - Power Heaven Co.,Ltd
Contract No.& Date(Materials) - 81/DPTSC(PTP)/2020-2021 (29.9.2021)
Contractor - Power Heaven Co.,Ltd
4. Contract Effective Date of Project - 10/2021
5. Completion Date of Project - 9/2023
(Approximation)
6. Complete Situation
Substation - 99.2 % (Until (13.2.2023))
(Completion of Work )
{Have Concreted Foundation to 66kV Gantry Foundation(6) Nos, GCB Foundation (4) Sets, CT Foundation (4) Sets, LA Foundation (5) sets, DS Foundation (4) sets, DSE Foundation (4) Sets, VT Foundation (1) Set & 230kV Gantry Foundation (4) Nos, CT Foundation (1) Set, GCB Foundation (1) Set, LA Foundation (1) Set, DS Foundation (3) Sets, 66kV Cable Duct & 230kV Cable Duct (100%) completed} { Flooring works are underway}
230kV Minhla Substation (66kV Brick Cable Duct,Brick Work & Cable Trench Rail Installation Work, 230kV Cube Bus Concreting Work)