Kayin State


­

 

230kV (Thaton – Mawlamying)-Hpa-An Transmission Line (8.43) miles and

230/66/11kV, (2x50) MVA Hpa-An (Sadan) Substation

1. Location                                                    -   Karean State, HpaAn Township.

2. Scope of Work            

    (A)  Line                                                      -  (8.43) miles

    (B)  Substation                                                                    

          230kV Incoming Bay                            -   2 Bays

          230kV Transformer Bay                        -  2 Bays

          230kV Bus Coupler Bay                       -   1 Bay

          230kV Measuring Bay                          -   2 Bays

          66kV Incoming/ Main                            -  2 Bays

          66kV Bus Section Bay                          -  1 Bay

          66kV Outgoing Bay                              -   6 Bays

          66kV Measuring Bay                            -   2 Bays

3. Situation of Signing Contract         

    (A)  Line

          Construction                                         -   Project Manager (3) + (Civil) Southen

          Contract No. & Date (Materials)           -   11/ DPTSC (PTP)/2019-2020 (30.3.2020)

          Contractor                                             -  Zillion Luck Engineering Co.,Ltd            

    (B)  Substation

          Construction                                         -   Project Manager (3) + (Civil) Southen

          Contract No. & Date (Materials)           -   88/ DPTSC (PTP)/2019-2020 (15.6.2020)

            Contractor                                           -  Zeya & Associates Co., Ltd

4. Starting Date of Project (Effective date) -  (17.7.2020)             

5. Ending Date of Project (Approximation)-  Line     - January, 2023

6. Complete Situation                                   -  Line     - (100 %)

                                                                           Substation (Switchyard Foundation) (Civil Work)   - (100%)

                                                                           Substation (Installation)   - (100%)

 

  230kV (Thaton – Mawlamying)-HpaAn Transmission Line

 

  230/66/11kV, (2x50) MVA HpaAn Substation