Under Construction Projects of Line and Substations in Rakhine State
No. |
Projects |
Substation |
MVA |
Location |
1 |
66kV RatheTaung- ButheeTaung - Mg Taw Line (42.66) miles and Substations |
ButheeTaung Mg Taw |
66/11kV ,2x5 MVA 66/11kV ,5 MVA
|
ButheeTaung, Mg Taw, Rakhine State. |
(1) 66kV RatheTaung-ButheeTaung-Mg Taw Line (42.66) miles and Substations
1. Location
Rakhine State, RatheTaung , ButheeTaung , Mg Taw |
2.Amount of Work
66kV Ponnagyun-RatheTaung-ButheeTaung-Mg Taw Line (42.66) miles
66/11kV ,2x5 MVA ButheeTaung Substation
66/11kV ,5 MVAMg Taw Substation and
3.Situation of signing Contract
Contract No. -38/MEPE(PTP)/2015-2016
4.Starting Date of Project −30-3-2016
5.Ending Date of Project −2018, December
6.Complete Situation −66kV Rathedaung-Buthidaung Line (100%)
66kV ButheeTaung-Mg Taw Line (84.36%)
66kV Buthidaung Substation (100%)
(30.10.2018)Already Energized the Line & Substation.
66kV Mg Taw Substation (100%)
(23.12.2018)Already Energized the Line & Substation.