Renovation Works of the Tharkeyta Power Plant (State Owned)

Project Location                 -    Yangon Region, in the compound of old Tharkeyta Power Plant

Contractor                          -    Marubeni Power and Infrastructure Systems Corporation

Project Type                       -    State Owned

                                                The contract has been signed between Electric Power Generation Enterprise and the Marubeni Power and Infrastructure Systems Corporation to renovate the 3                                                    Gas Turbine Financed by JICA

Machine Type                     -    GT (Frame-V, Mark- II)

Current Capacity                -    GT (3 x 19 MW)

Renovated capacity            -    GT (3 x 21.8MW)

Gas Consumption               -    27 MMCFD

Project Consultant              -    Joint venture between Tokyo Electric Power Services Co.,Ltd & Oriental Consultants Co.,Ltd

Current Status                    -    The renovation work of GT No.(2) had finished and it is operating in accordance with the electricity demand. Currently contractor is executing the renovation work                                                   of GT No.(3) and GT No.(1).

 

Rehabilitation Works of Transmission System in Yangon (Ahlone, Hlawga, Ywama, Tharkayta)

Project Location                 -    Yangon Region (Ahlone, Hlawga, Ywama, Tharkayta

Contractor                         -    Mitsubishi Corporation

Project Implementation       -    EPC (Engineering, Procurement and Construction) contract has been signed between Electric Power Generation Enterprise and Mitsubishi Corporation dated on                                                   29th May, 2018, to rehabilitate the Transmission System of Ahlone, Hlawaga, Ywama and Tharkeyta Sub-Station financed by JICA

Project Consultant              -    Joint Venture between Tokyo Electric Power Services Co.,Ltd & Oriental Consultants Co.,Ltd

Current Status                    -    Currently contractor is importing the substation equipment from the aboard and Implementing the Substation renovation works. Currently renovation work of                                                           Hlawga substation had finished and other 3 substations are under renovation.

 

Rehabilitation, Operation, Maintenance and Management (ROMM) of

Hlawaga Power Plant (Private Owned)

Project Location                 -    Yangon Region, in the compound of old Hlawaga Power Plant

Company                           -    Golden Green Energy Co.,Ltd

Project Type                       -    ROMM (Private Owned)

                                            -    The PPA (Power Purchase Agreement) contract has been signed between Electric Power Generation Enterprise and Golden Green Energy Co.,Ltd dated on                                                          30th  November, 2018, for the Rehabilitation, Operation, Maintenance and Management (ROMM) of Hlawaga Power Plant

Machine Type                     -    GT (Frame-6, Mark- V)

                                             -    STG (V63, CS-3000)

Current Capacity                -    70 MW

Renovated capacity            -    84 MW

Gas Consumption               -    26 MMCFD

Current Status                    -    Because the project is stopped, Electric Power Generation Enterprise and Project Company are discussing to resume the project.

 

Ywama 300MW Combined Cycle Power Plant Project

Project Location                 -    Yangon Division, in the compound of Ywama Power Plant

Company                           -   

Project Type                       -    State Owned (World Bank Loan)

Contracted Capacity           -    300MW

Current Status                    -    Financing Agreement for Ywama Project has been signed between Ministry of Planning and Finance and World Bank dated on 3rd July 2020.

                                         -    EPGE issue the prequalification tender for Contractor dated on 11th June 2020 and close dated on 20th August 2020. EPGE is reviewing the tender documents.

                                         -    EPGE sent the Request for Proposal (RFP) to the Short- listed Consultant date on 28th January 2021.

                                         -    Currently the project is pending because World Bank halted the financing for the World Bank loan projects in Myanmar.

 

Upgrading of 50MW Gas Turbine Power Plant to Combined Cycle Power Plant

Project Location                 -    Yangon Division, in the compound of Thilawa Power Plant

Company                           -   

Project Type                       -    State Owned (JICA Loan No. MY-P32)

Current Status                    -    JICA Loan Agreement No. MY-P32 for the Thilawa Project has been signed between Ministry of Planning and Finance and JICA dated on 31st March 2020. Currently EPGE is preparing the Term of Reference (TOR) for Short-listed Consultant Tender with the JICA.