Transmission Lines and Substations under Project by Germany KfW (Kreditanstalt fur Wiederaufbau) Loan by Rural Electrification Programme II (Grid Extension) in Southern Shan State
(1)Location
|
416 villages in Taunggyi, Loilem, Linnkhae Districts, Shan State (South) |
(2) Project Amount
Construction of 66 kV, 33 kV, 11kV Transmission Lines and Substations
(3) Condition of Contract
Funded Sources (Loan) − Germany KfW (Kreditanstalt fur Wiederaufbau)
Contracted Date − 21.9.2017
(4)Project Starting Year −2017
(5) Project Completing Year (Estimated) − (2021-2022)
(6) Progress Condition − Tender is being prepared to bid International Consultant Firm