MINISTRY OF ELECTRIC POWER

Breaking News :

Department New

Complete the construction of 230 kV Thanlyin-Thilawar Transmission Line and Substation by JAPAN ODA Loan

The construction of 230 kV Thanlyin-Thilawar transmission line (10.07 miles) and 230/33/11kV (3x100MVA) Thilawar Substation was started by Toenec Corporation on 9.3.2016 and completed on 20.11.2017. Therefore, MOEE can supply the electricity on that day (10:11) hrs. This Project was implemented with JAPAN ODA Loan and cost 3147 Million Yan. This can supply the electricity to Thilawar Special Economic Zone and its sourrounding area.


Read More...
26-Dec-2017