MINISTRY OF ELECTRIC POWER

Breaking News :

Construction of 66 kV Myingyan- Ngazun Transmission Line (0.67 miles) and 66 /11 kV 10 MVA Ngazun Substation Project

     

  15 November 2018

        Construction of 66 kV Myingyan- Ngazun Transmission Line (0.67 miles) and 66 /11 kV 10 MVA Ngazun Substation Project As construction of 66 kV Myingyan- Ngazun Transmission Line (0.67 miles) and 66 /11 kV 10 MVA Ngazun Substation Project was started to construct on 7.3.2016 to fully electrify to Ngazun, Mandalay Region, transmission line was charged on 31.5.2018 and Ngazun Substation was completed on 1.8.2018 . So, 1 town, 158 villages and 27029 households near Ngazun will distribute electricity from national grid round the clock.

Post under by : Department of Power Transmission and System Control (DPTSC)
15-Nov-2018